This area of Bear Canyon Creek experienced erosion and sedimentation during the 2013 flooding. The project improvements include channel restoration (two boulder drop structures) along 200 linear feet of Bear Canyon Creek, as well as a new outfall for an existing 24” storm sewer located in Ithaca Drive.
DBC provided topographic survey, design drawings, utility locates, GIS deliverables, and bid and construction support for the project. We also secured City of Boulder Wetland and Floodplain Development Permits. The project was completed in 2019 and constructed in 2022. After coordination with MHFD and FEMA, the follow-up LOMR was approved in 2024.